By Vvon Engineering Team | Published | Updated
Prepare a gamma-camera room using the selected system’s site-planning documents: delivery access, structural checks, power, cooling, cable routes and readiness records.
Nuclear medicine RFQ checklist (TXT)
Prepare the room and delivery route against the selected manufacturer's site-planning documents. Crate dimensions, floor and lift capacity, turning space, utilities and environmental conditions need confirmation with the qualified project team. This guide covers site readiness; the installation timeline shows how readiness fits into procurement and handover.
Every manufacturer issues a site planning pack for the specific configuration you bought. Get it at contract signature, before the room is chosen, and issue it to the civil contractor as a contract document rather than as background reading. If the contractor has not priced against it, the contractor will not build to it.
Read the service access clearance twice. A camera installed hard against a wall works perfectly until the first detector service, when the engineer cannot open the cover and the hospital pays to move the wall.
The structural assessment must consider total mass, concentrated loads, load distribution, dynamic effects where relevant, shielding and the delivery route. A mass or point-load figure alone does not determine a particular slab failure mode.
Have a structural engineer check the actual slab against the site planning figures, with the reinforcement drawings if they exist. In a conversion where the drawings are missing that means a physical investigation, and it takes time. Start it early.
Assess temporary transport loads and lifting arrangements as well as the final equipment position. Wheel or support loads depend on the selected handling equipment and are not automatically greater than every installed gantry load.
Two further structural points. If the room is on an upper floor, the shielding walls add dead load on top of the equipment load and the two are assessed together. And where the site plan states a floor flatness tolerance, treat it as a real constraint: a gantry that cannot be levelled within its adjustment range means re-screeding a floor after the epoxy has been laid.
That last point is where projects lose equipment. A crate left in a corridor beneath a leaking air conditioning condensate drain through a monsoon week becomes a warranty argument that nobody wins, and the hospital is the party with the least bargaining power.
Confirm the actual voltage, phases, frequency, available capacity and quality against manufacturer requirements. Qualified electrical staff should assess voltage variation, interruption, transients and protective arrangements; a nominal supply label alone does not demonstrate suitability.
Obtain an engineered supply and protection plan compatible with the manufacturer and applicable electrical requirements. Define distribution, isolation, protective earthing and equipotential bonding, surge protection, backup power and changeover. Do not prescribe a separate unbonded earth pit, universal stabiliser or arbitrary resistance target. Agree testing, records and periodic verification with qualified electrical staff. A changeover does not necessarily produce a damaging surge, and backup scope must be established for the whole supported configuration.
Investigate electrical reliability from measurements, fault records and manufacturer requirements rather than assuming one national failure mechanism.
Size environmental control from equipment heat loads, occupancy, building conditions and specified operating and storage limits. Assess redundancy and continuity needs; two identical full-capacity units are one possible design, not a universal requirement.
Maintain manufacturer conditions during use and shutdown, including permitted rates of temperature change and humidity. Whether continuous active cooling is required depends on the room and equipment; compare continuity and lifecycle costs without inventing a universal annual electricity-versus-crystal price ratio.
Assess condensation risk, ventilation, control of humid air and recovery after a cooling failure. Coordinate these with the approved facility ventilation and electrical design. An environmental log supports investigation but cannot by itself prove or exclude every cause of a fault.
Agree acceptance methods and responsibilities before installation. Manufacturer tests and independent physics assessment should document compliance with the purchase specification and suitability for clinical use. Handover does not extinguish the supplier's warranty or other contractual obligations.
| Item | Ready means | Signed off by |
|---|---|---|
| Room dimensions and clearances | Measured on site against the site plan, including door swing and service access | Project engineer |
| Floor | Load checked against point and distributed figures, level within tolerance, finish laid and cured | Structural engineer |
| Shielding | Installed, inspected before closing, photographed at every seam and penetration | Medical physicist |
| Power | Manufacturer-compatible supply, protection, backup and changeover verified under the electrical design | Electrical engineer |
| Earthing | Protective earthing and equipotential bonding tested and recorded by qualified electrical staff | Electrical engineer |
| Air conditioning | Specified temperature and humidity demonstrated with agreed continuity arrangements | Facilities |
| Ducts and cable routes | Installed, clear, pull cords in place, network drops terminated and tested | Project engineer |
| Delivery route | Surveyed end to end, obstructions removed or scheduled, lift capacity confirmed | Project engineer |
| Regulatory | Licence application filed, shielding design and survey reports submitted | Radiation safety officer |
Review readiness against the real project schedule and dependencies. Assign each outstanding item an owner, due date and evidence of completion; a fixed fortnightly meeting or eight-week threshold does not suit every installation.
Send Vvon the room drawing, access route and intended system configuration for a site-planning enquiry. Confirm manufacturer planning documents, survey scope, installation responsibilities and qualified design work in the proposal. Contact +8801805987890 or info@vvon.com.bd.
Share your application, equipment requirements and procurement timeline. Our engineers can help clarify the configuration and scope for your enquiry.