Skip to main content

Planning a laboratory building or refurbishment: the decisions that are expensive to reverse after handover

By Vvon Engineering Team | Published | Updated

Bench layout, services routing, floor loading and storage decided in the right order, plus the commissioning tests worth holding retention against, for anyone building or refitting a laboratory block in Bangladesh.

Scientific & laboratory RFQ checklist (TXT)

Plan equipment access and utilities before freezing a laboratory refurbishment. A rig’s packed dimensions, electrical supply or exhaust route can change the building brief, and resolving those interfaces on drawings is usually easier than after construction.

Laboratory buildings are unusual because the fit-out drives the structure rather than the other way round. What follows is the order in which decisions should be taken, and which of them become permanent once the contractor leaves site.

Write the equipment list before the architect draws anything

The single most valuable document in a laboratory project is a schedule of every item that will ever stand in the room, with its footprint, weight, services requirement and access route. It does not have to be a purchase decision. It has to be an honest expectation, including the equipment you hope to buy in five years.

Give the design team, for each item: length, width and height; operating weight including contained water or product; electrical supply, phases and connected load; water supply and drain requirement; gas requirement; extraction requirement; heat rejected into the room; noise; and whether it must sit against a wall, a window or a door. State the crated dimensions and weight too, because that governs the access route, not the installed size.

Departments resist this because it feels premature. It is not. An architect designing a laboratory without an equipment schedule will produce a well-proportioned classroom with sinks.

Bench layout and circulation

Layout is where teaching quality and safety are decided, and where a small change on the drawing has a very large effect on how the room works.

On accessibility: level thresholds, at least one bench position at seated working height, and clear turning space are straightforward at design stage and close to impossible afterwards. Include them.

Services: what to get right at first fix

ServiceGet this right at designWhat it costs to change later
Electrical distributionDedicated board with spare ways, per-bench isolators, three-phase to named positions, containment sized with spare capacityHigh. Surface trunking, trailing leads and a board with no spare way, permanently
EarthingCompliant protective earthing and equipotential bonding, with instrument EMC requirements coordinated by the electrical designerVery high. Retrofitting an earth into a finished building is disruptive and often compromised
Water supplySupply capacity and quality matched to equipment, with appropriate isolation and approved backflow protectionModerate for a branch, high for a new riser
DrainageChemically compatible collection and drainage, with segregation and treatment for the actual waste; dilution is not a substitute for complianceVery high. Falls are set in the screed and cannot be adjusted
GasCylinder store outside with ventilation and restraint, reticulated lines with isolation at the point of use, fixed detectionHigh. Cylinders end up inside the laboratory, which is the arrangement everybody regrets
ExtractionRiser space and duct routes reserved, discharge above the roofline away from intakes, make-up air path, fan position and mountingVery high. A duct route not reserved at design cannot usually be created
Compressed airCompressor sited away from teaching space, receiver, refrigerant dryer sized for local humidity, ring main with drop legs and drain pointsModerate for the ring main, high for the plant space
Cooling and ventilationSized for the heat rejected by the equipment, not just for occupancyHigh, and undersized cooling shows up only in April

Size compressed-air treatment for the manufacturer’s required quality and the site’s ambient conditions. Locate ventilation discharges using a re-entrainment assessment. Establish chemical and biological waste segregation before designing drains, and reserve data routes with suitable separation from power cables.

Standby supply and the load-shedding question

Classify each load by the consequence of interruption and its safe shutdown requirements. Coordinate instruments with their cooling, extract, gas and control auxiliaries. Heaters and motors cannot automatically be excluded from essential power if they support a critical process or safety function.

Floor loading, vibration and the quiet corner

Structural decisions are the truly irreversible ones, and laboratory loads are not what a general office floor is designed for.

Storage, and why every laboratory is short of it

Ask any laboratory manager what they would change and storage comes up more often than equipment. Storage takes floor area away from the visible teaching function, so it is the first thing trimmed when the plan is squeezed.

  1. A separate chemical store with segregated cabinets, ventilation and a lockable door, not a cupboard at the back of the teaching room.
  2. A cylinder store outside the building, shaded, ventilated, with cylinders restrained and full and empty separated.
  3. A technician's workshop or preparation room adjoining the laboratory. Setting up an experiment for twelve groups is not something that can be done in the room while a class is in it.
  4. Storage for accessories that are not in use, plus a spares cupboard with an inventory. A hydraulics bench with eight accessories needs somewhere for seven of them that is not the floor, and imported spares only protect you if they can be found.
  5. Somewhere for student bags near the door, outside the working zone. Without it, bags go under benches and become a trip hazard in exactly the wrong place.

Commissioning: hold retention against tests, not against delivery

Write the acceptance criteria into the contract at tender stage. Once the building is handed over and the retention released, your bargaining position is gone.

What it costs to change your mind

DecisionChange during designChange during constructionChange after handover
Room size and door widthsA drawing revisionStructural reworkUsually impossible
Drainage falls and gully positionsA drawing revisionScreed rework, some delayCut the floor, lose the finish
Fume cupboard duct routeA drawing revisionRiser and ceiling coordinationOften no route exists at all
Electrical board capacity and spare waysMarginal costBoard replacementNew submain and containment across a live building
Earthing arrangementMarginal costModerateDisruptive and usually compromised
Bench positions and services outletsFreeModerateSurface conduit and trailing leads
Storage and preparation roomA planning decisionLoss of teaching areaCorridor cupboards and clutter

Every row in the right-hand column is a laboratory somebody is working in today. The items that cost the least to decide correctly are the ones that cost the most to fix, because they are buried in the fabric.

The equipment schedule should remain a controlled design document through construction, commissioning and future expansion.

Have a project to scope?

Share your application, equipment requirements and procurement timeline. Our engineers can help clarify the configuration and scope for your enquiry.

Discuss your requirements

Browse buying and selection guides | Back to all Insights