A walkthrough of the net metering approval route for BPDB, DPDC, DESCO, NESCO and REB consumers: which office receives the file, which documents it must contain, who prepares each one, and the errors that send an application back.
The engineering on a rooftop solar plant is rarely what delays it. The delay is usually a file sitting in a distribution utility office because the single line diagram was drawn without the existing transformer on it, or because the sanctioned load written on the application does not match the sanctioned load printed on the last bill. This is the net metering approval route as it is actually processed: which office takes the file, what goes in it, who prepares each item, and what sends it back.
Net metering in Bangladesh is governed by the Net Metering Guidelines 2025, issued by the Power Division and administered through SREDA. The guideline allows eligible consumers, both single-phase and three-phase, to install rooftop solar of up to 100% of their sanctioned load, and 80% of transformer capacity for MV consumers at 11 kV and above, and to export surplus generation to the grid. The utility nets imported and exported energy on the monthly bill. Any surplus at the end of the financial year is settled at the prevailing BERC bulk-purchase rate.
The reviewing engineer is not assessing whether solar is a sensible investment for you. They are assessing whether your plant can sit on their network without causing them a problem, and three questions decide it: does the declared capacity fit inside the sanctioned load and the transformer rating, will the inverter disconnect cleanly when the grid goes down, and can the metering be read and billed correctly. Every document in the file exists to answer one of those three.
The application does not go to SREDA. It goes to the distribution utility that issued your connection, and the receiving office depends on where the meter is, not where your head office is.
| Utility | Service area | Application office | Contact |
|---|---|---|---|
| DPDC | Dhaka city (east) | DPDC head office, Wari | 02-9556001 |
| DESCO | Dhaka city (north) | DESCO head office, Mirpur | 02-8034400 |
| BPDB | Outside Dhaka, major cities | Divisional/district offices | 16196 |
| REB/PBS | Rural areas | Local PBS office | Varies |
| NESCO | Rajshahi, Rangpur divisions | NESCO head office, Rajshahi | 0721-775060 |
Two consequences follow. DPDC and DESCO split Dhaka between them, so a Tejgaon site and a Mirpur site are separate applications to separate organisations with separate queues, even where one company owns both. And a large share of Bangladesh's agro processing, cold storage, feed and rice milling capacity sits on a Palli Bidyut Samity connection, where the file starts at the local PBS office and is escalated for approval. That handling step has nothing to do with your plant and everything to do with internal routing. Put it in the programme rather than discovering it in month three.
The file is short. What makes it slow is that roughly half of it comes out of the applicant's own records and half out of the EPC contractor's engineering, and the two halves have to agree with each other and with what the utility already holds on your account. Most returned applications are returned over an inconsistency, not an engineering objection.
| Document | Who produces it | What it must agree with, and the usual problem |
|---|---|---|
| SREDA-format application form | Applicant signs, EPC completes the technical fields | Consumer name and account number must match the utility's records exactly, including spelling carried over from an old trade licence |
| Single line diagram (SLD) | EPC contractor | Must show the existing transformer, incoming breaker, AC combiner, protection settings and the net meter position, not only the PV side of the wiring |
| Module and inverter datasheets | EPC contractor | The inverter needs recognised grid protection and anti-islanding certification, and the model on the datasheet must be the model that actually arrives on site |
| Roof plan and array layout | EPC contractor, from the site survey | Array area has to be consistent with the declared kWp; walkways, setbacks and inverter platforms left off at this stage force a revision later |
| Recent electricity bill | Applicant | The sanctioned load printed on the bill is the number the utility sizes your approval against, whatever your connected load has grown to |
| NID or trade licence | Applicant | Must be in the same name as the electricity account; a plant bought from another company needs the name transfer completed first |
| Load and generation summary | EPC contractor | Declared capacity against sanctioned load, and against transformer rating where the MV ceiling applies |
One line on that table causes more trouble than the rest combined: sanctioned load. Plenty of Bangladeshi factories have added machinery across a decade without revising the sanctioned load on record. If your connected load has outgrown it, resolve that first, as a separate matter, before the net metering file goes in. A load enhancement application and a net metering application moving through the same office at the same time will slow both.
The commissioning test is a joint exercise between the utility and the EPC contractor, and it goes quickly when the contractor turns up prepared. Expect the inverter to be tripped by simulating a grid outage so the anti-islanding function can be observed, earthing and insulation resistance to be measured, protection settings to be read back from the inverter, and the meter registers checked in both directions. Have the as-built SLD, string test records, earthing test result and printed inverter setting sheets physically on site, and send the electrician who commissioned the plant rather than a project supervisor, because the questions are usually settings questions. Keep your own signed copy of everything: a year later, when a meter is replaced or a billing query opens, that record is the fastest way to settle it.
Under net metering your monthly bill is calculated as grid import in kWh less solar export in kWh, multiplied by the tariff rate. If the plant generates more than the site consumes in a month, the surplus carries forward as a credit against the next month's bill. At the end of the financial year, on 30 June, any remaining credit is settled at the bulk purchase tariff. In practice a well-sized industrial system shows a near-zero net import bill for eight to ten months of the year, with the remaining months reflecting shorter, cloudier winter and monsoon generation days.
Check the first bill against your monitoring platform's export total for the same period. If the meter was configured with the export register the wrong way round, it shows up immediately as an unexpectedly large import figure, and it is far easier to correct in the first cycle than after six months of accumulated error.