Skip to main content

Net Metering Application in Bangladesh: Online Form, Documents and Steps

By Vvon Engineering Team | Published | Updated

Find the official Bangladesh net-metering application portal, identify your utility and prepare the account, site and engineering information for submission.

Solar EPC & street lighting RFQ checklist (TXT)

To start a net-metering application in Bangladesh, open the government's Net Energy Metering portal, identify the utility shown on your bill and check the current account and project requirements. This guide explains the application file and utility coordination. Use the separate economics guide for sizing and bill-saving assumptions.

Buying questions, answered

Where should I start a net-metering application in Bangladesh?

Check the utility named on your electricity bill and the government's Net Energy Metering application portal. Confirm the current submission route and document requirements for that account. The utility decides the application; VVON can discuss engineering and coordination within a defined EPC scope.

What should I send VVON before requesting an EPC proposal?

Send the site location, recent electricity bills, daytime operating schedule, roof or land information, photographs and target date. Identify backup requirements separately. Use the solar configuration guide and request a site-specific project proposal.

What the utility is actually approving

The 2025 guideline defines system capacity using aggregate inverter AC output. Clause 3.3 limits AC output to sanctioned load and, for medium- to extra-high-voltage consumers, to 80% of the transformer or parallel-transformer rated capacity. These are not direct limits on module DC kWp. Confirm the proposed design and any applicable additional conditions with the utility.

The application review covers the proposed connection and its compliance with the applicable requirements. Capacity, protection, equipment evidence and metering are key checks, alongside the account, design and site records required by the serving utility. Keep the investment appraisal and the utility-approval file distinct, and reconcile the equipment and capacity stated in both.

Which utility takes your file

The application does not go to SREDA. It goes to the distribution utility that issued your connection, and the receiving office depends on where the meter is, not where your head office is.

Supplying utilityWhere to start
DPDC / DESCOUse the customer account to identify the responsible office and current application channel.
BPDBUse the office shown on the bill.
BREB / PBSContact the supplying Palli Bidyut Samity.
NESCO / WZPDCLConfirm the responsible office from the account.

Use the site's actual consumer account, not the company head-office address or a broad district map. Obtain the receiving office and required submission channel from the utility.

Who is eligible

The application file, item by item

Prepare the owner's account and property records alongside the contractor's technical annexures. Check that names, capacities, equipment and drawings agree before submission.

DocumentWho produces itWhat it must agree with, and the usual problem
SREDA-format application formApplicant signs, EPC completes the technical fieldsConsumer name and account number must match the utility's records exactly, including spelling carried over from an old trade licence
Single line diagram (SLD)EPC contractorMust show the existing transformer, incoming breaker, AC combiner, protection settings and the net meter position, not only the PV side of the wiring
Module and inverter datasheetsEPC contractorThe inverter needs recognised grid protection and anti-islanding certification, and the model on the datasheet must be the model that actually arrives on site
Roof plan and array layoutEPC contractor, from the site surveyArray area has to be consistent with the declared kWp; walkways, setbacks and inverter platforms left off at this stage force a revision later
Recent electricity billApplicantThe sanctioned load printed on the bill is the number the utility sizes your approval against, whatever your connected load has grown to
NID or trade licenceApplicantMust be in the same name as the electricity account; a plant bought from another company needs the name transfer completed first
Load and generation summaryEPC contractorDeclared capacity against sanctioned load, and against transformer rating where the MV ceiling applies

Resolve discrepancies in sanctioned-load and account records with the utility. If a load revision is proposed, ask how it should be sequenced with the net-metering application rather than assuming parallel submissions always delay each other.

The sequence, from feasibility to first netted bill

Where applications stall

The commissioning test, and what to have ready

Use the utility's approved commissioning and witness plan. Qualified personnel should verify protection, isolation, metering and the required electrical tests without exposing occupants or essential services to an uncontrolled interruption. Retain signed results, settings and as-built drawings.

What the first netted bill looks like

Under clauses 3.4–3.5 of the 2025 guideline, billing credits are reconciled quarterly after March, June, September and December. The guideline deducts 10% of net exported electricity as a distribution maintenance charge before crediting the remaining 90%. Residual settlement uses the applicable BERC bulk rate; fixed charges can remain. Check the signed agreement and current utility billing implementation when modelling value.

Compare utility import/export registers for the same period with appropriately configured site metering. An inverter's generation total is not the export total. Check CT ratios, direction and period alignment before concluding that a billing difference is a meter fault.

Sources and project checks

Consult the relevant edition and the documents for the exact equipment and site: Power Division / SREDA: Net Metering Guidelines 2025, English; IEC 62446-1: grid-connected PV documentation and commissioning.

Plan your next step

Check the inputs behind your net-metering proposal

A useful sizing discussion starts with how the site uses electricity, not only how many panels fit on the roof. Ask for a model you can review with your finance and facilities teams, with the connection assumptions shown separately from the proposed equipment capacity.

Rooftop system selection: Compare configurations for the operating pattern.

Solar project assessment: Review the engineering and installation scope.

Discuss net-metering project sizing

Browse buying and selection guides | Back to all Insights

Prepare the application and the engineering brief separately

The Power Division portal explains the application stages. VVON can discuss the EPC engineering scope; the relevant utility decides permission and system acceptance.

Official application portal

Start with the electricity account and applicant details requested by the official portal.

Confirm in the offer: Consult its current user guide and utility-specific requirements before submitting.

Explore Official application portal

Installation permission

Keep the approved project information with the equipment and installation records.

Confirm in the offer: Do not treat an EPC quotation as utility permission or a guaranteed approval date.

Explore Installation permission

EPC engineering scope

Define survey, electrical design, equipment, installation and application-support deliverables.

Confirm in the offer: Agree who supplies metering documents, inspections, commissioning evidence and handover records.

Explore EPC engineering scope
Prepare a comparable quotation
  • Electricity account, utility, sanctioned load and site address
  • Proposed system arrangement and equipment documentation
  • Named owner, EPC and utility responsibilities
Reference information
Discuss your shortlist