Assess occupancy, seasonal demand, roof appearance, coastal exposure and separate backup requirements for hotel solar.

Solar EPC & street lighting RFQ checklist (TXT)

A resort general manager can usually tell you two numbers without looking them up: the electricity bill in peak season and what the generator burned last month. Neither number is improved by a solar plant that was designed for a factory roof and dropped onto a hotel, because a hotel is a different load, a different roof and, on the coast, a different environment altogether.

A load that never stops, meeting a supply that does

Hotels run around the clock, but not evenly. Guest room air conditioning peaks in the afternoon and again overnight. Corridor and facade lighting, the restaurant and the banquet hall are evening loads. Laundry, kitchen preparation, housekeeping, pool filtration, water pumping and the office block are firmly daytime, and those are the loads a rooftop array will actually displace.

Measure daytime demand at different occupancy levels and compare it with a seasonal generation model. A low-season profile is a useful starting point, but the chosen size should also account for export terms, roof constraints and the full financial case.

Review whether laundry, pool filtration and pumping can operate during solar hours without affecting hygiene, guest service or equipment limits. Include staffing and control changes in the cost of any revised schedule.

Where the panels can actually go

A hotel roof is the most contested piece of real estate on the property. Before any array is drawn, walk every roof with the chief engineer and mark what is already there and what is promised to somebody else.

What the coast does to the specification

Cox's Bazar, Kuakata, Saint Martin's and the rest of the coastal belt combine salt laden air, high humidity, driven rain and cyclone season wind. A specification written for a Dhaka rooftop will corrode there, and the failures are slow, ugly and expensive to reverse.

Solar is not back-up power, and guests will find out

This is the conversation to have early, because the expectation is almost always wrong. A grid tied inverter is required to disconnect when the grid fails. It is an anti islanding protection function, it is not optional, and it means that during a load shedding event the array stops even at noon under a clear sky. A hotel that installs solar and still loses the lifts in a power cut has not been badly served. It has been correctly served and badly briefed.

There is a second interaction that catches properties which run a generator regularly. When the hotel is on the diesel set, an array feeding the same board can push the generator into reverse power, which its protection will not tolerate and which can damage the machine. The answer is a controller that either blocks the inverters or limits them to the measured on site load while the generator is running, and it has to be commissioned and tested with the generator, not assumed.

Define backup requirements with the hotel's electrical and fire-safety designers. Life-safety loads, fire pumps and lifts have specific starting, autonomy and supply requirements and must not be added casually to a general battery board. Price the approved scope rather than assuming it is small or inexpensive.

Hill sites and weak spurs in Sylhet

Resorts in the Sylhet hills and the tea belt have the opposite set of problems. Salt is not the issue. The issues are a long low tension spur from a distant transformer, voltage that swings enough to trip inverters on their own protection settings, tree lines that shade the array for part of the day and grow taller every year, rainfall that overwhelms a badly detailed roof, and site access that decides how big a delivery can reach the property at all.

Log supply voltage to identify grid and cable issues before choosing a design. Keep protection settings within the utility-approved configuration; a poor local supply is not a reason to widen trip limits without approval. Include existing trees and realistic future obstructions in the shading assessment.

Hill sites also make the earthing and lightning protection more than a formality. Exposed ridge positions, tall structures and a hospitality building full of guests is not a combination to leave to a token earth rod. Specify the earthing design, measure the resistance at commissioning and record it.

Sources and project checks

Consult the relevant edition and the documents for the exact equipment and site: SREDA: Net Metering Guidelines and current application documents; IEA PVPS: operational and economic impacts of extreme weather; JinkoSolar: model datasheets, certificates, installation manuals and warranties.