By Vvon Engineering Team | Published | Updated
Rice mills run hard through Boro and Aman and idle between. How that duty cycle changes solar sizing, what a husking shed roof can carry, how the export credit absorbs the quiet months, and what to ask an EPC contractor.
Solar EPC & street lighting RFQ checklist (TXT)
Rice-mill demand follows intake, drying, milling and storage. Use the actual production calendar and full-year records rather than treating the mill as a constant load.
Compare local seasonal generation with the mill's harvest and processing periods. Harvest timing alone does not prove that peak solar production coincides with peak demand.
The complication is the dryer. Husking and whitening draw a fairly steady demand once the line is running, but dryer load rises with the moisture content of incoming paddy, which is why an Aman season in a wet year can push peak demand well above what the same mill drew in Boro. If load profiling happens to be done in a dry week, the dryer is under-represented and the plant is undersized against the one peak that matters.
| Input | Evidence needed | Why it matters |
|---|---|---|
| Consumption | Twelve months of bills and representative interval demand | Separates direct use, exports and changing demand. |
| Generation | Location, layout, weather dataset and loss assumptions | Estimates output month by month. |
| Connection | Sanctioned load, transformer and utility requirements | Establishes eligible capacity and approval conditions. |
| Installed cost | Dated itemised quotation and exclusions | Includes roof work, connection and commissioning. |
| Operating cost | Maintenance, insurance and replacement assumptions | Avoids treating later electricity as cost-free. |
Calculate generator energy cost from recorded fuel, loading and maintenance. Then establish how the proposed architecture could safely displace those hours; ordinary grid-following PV stops during an outage.
Compare several capacities against interval demand and seasonal generation. Annual average consumption alone cannot prove year-round self-consumption.
Under clauses 3.4–3.5 of the 2025 guideline, billing credits are reconciled quarterly after March, June, September and December. The guideline deducts 10% of net exported electricity as a distribution maintenance charge before crediting the remaining 90%. Residual settlement uses the applicable BERC bulk rate; fixed charges can remain. Check the signed agreement and current utility billing implementation when modelling value.
The 2025 guideline defines system capacity using aggregate inverter AC output. Clause 3.3 limits AC output to sanctioned load and, for medium- to extra-high-voltage consumers, to 80% of the transformer or parallel-transformer rated capacity. These are not direct limits on module DC kWp. Confirm the proposed design and any applicable additional conditions with the utility.
Most mills are corrugated metal sheet on light steel trusses, sometimes on timber in older husking units, spanning the milling hall and the attached godowns. The roof is rarely one plane. Mills grow by extension, so a single site can carry sheds of three different ages, three purlin spacings and three states of corrosion. Check purlin spacing and section before anyone quotes a mounting structure, and get the structural certificate signed: a missing or unsigned certificate is one of the more common reasons an application is sent back.
Select mounting for the exact roof profile and verified load path, with compatible waterproofing. Include silos, elevators and dryer stacks in the seasonal shading assessment.
If outage support is needed, compare generator-aware PV controls, UPS and compatible battery arrangements. Model actual fuel displacement and supported loads; no generic diesel-reduction percentage or payback follows from choosing hybrid.
A caution on battery sizing: a bank large enough to carry the whole milling line through a long outage is rarely worth the money. What is worth protecting is the equipment where an interruption costs a batch or a restart, meaning the dryer and its fans, the elevators, the control panels and the instrumentation. Agree that schedule with the mill manager, then size the battery to it.
Identify the utility from the mill's electricity account. Use its current application checklist rather than relying on a district-level generalisation.
Consult the relevant edition and the documents for the exact equipment and site: Power Division / SREDA: Net Metering Guidelines 2025, English; SMA: PV-diesel control and minimum generator loading; US Department of Energy: battery energy storage procurement checklist; IEA PVPS: operation and maintenance in different climates.
Share your application, equipment requirements and procurement timeline. Our engineers can help clarify the configuration and scope for your enquiry.